- "When we used it, the project plans ran to scores of pages with hundreds of tasks and we didn't have a clue about what was going on".
- "Project gives funny answers. " they say.
- Those who don't use Project because of these issues, then report proudly how they keep it "simple" by using Excel and, if they use Project it's only to do a Gant Chart that they paste into PowerPoint.
"Keep it simple and enjoy complex benefits. Why don't you simply require your organisation to have for each "project" one-line plans in Microsoft Project?"
That floors them. "That can't possibly be enough detail", I hear.
I think that level of detail for most organisations is much better than projects with hundreds of trivial or individually-managed tasks, or projects "planned in PowerPoint". Maybe once 1-line project plans are achieved, you can move on to 5 or 6 line project plans. But no more.
Here is an example.
See the screen shot where we have a project called "Project 6" with one task: "Do Project 6". This project is slated to start on 27th May 2008 and use four resources:

• 2 Geologists
• Half of James Roberts' time
• A small amount of Susie Thomas's time
• A little less than half of Anne West's time
Project computes the total cost, based on the billing rates for the above people, to be £133k.

But this isn't the only project or activity being done by the organisation. There are many more, and nicely each has their own one-line model. The following shows how all these line projects are pulled together into a single view in a master project

So what other benefits do we get by doing this simple project setup in a complex product like Microsoft Project:
- Project handles all the complicated time-based computations.
- If one resource file is used, we can use the built-in capability of Project to show resource commitments, clash, over/under allocation.
- Simple scheduling can start to occur, for example make sequence the 8 projects in some sort of order--not by priority by but by successor/predecessor links.
- Let Project do the work of telling you when the projects will get done. If you don't like the answer, then change the plan.